Planning Scheme for the Lay Out of a Biogas Plant (1
Step 1: establish gas requirement
Guide values for gas
consumption
Cooking: 0.25 m³ (8 cu ft) per person per day
Lighting:
0.12-0.15 m³ (4-5 cu ft) per hour per lamp
Driving engines: 0.75 m³
(17 cu ft) per kW per hour
Gas requirement per unit x No. of units = Total gas requirement
Example: 0.25 m³ per person and per day X _4_ persons =__1.0__m³
Gas requirement for cooking: 0.25 m³ per person per day X
_________persons =__________m³
Gas requirement for lighting: 0.15
m³ per lamp per hour X ___________lamps =___________m³
Gas
consumption of engines: 0.75 m³ per kW per hour X ________operating hours =
______m³
Gas requirements for other processes:
_________X__________=__________m³
- Refrigeration _________X__________=__________m³
- Drying plant _________X__________=__________m³
- Production __________m³
Total gas requirement per day
Is this gas requirement likely to satisfy needs in 5 years?
Z Additional gas requirement _________X__________=__________m³Total gas requirement _____________m³
Step 2: establish gas production
Gas generation - guide
values
Type |
Manure (moist) per day |
Gas per kg per day |
Gas yield per animal |
1 head of cattle |
10 kg |
361(1.3 cu ft) |
3601(13 cu ft) |
1 water buffalo |
15 kg |
361(1.3 cu ft) |
5401(19.5 cu ft) |
1 pig (approx. 50 kg) |
2.25 kg |
781(2.8 cu ft) |
1801(6.3 cu ft) |
1 chicken (approx. 2 kg) |
0.18 kg |
62 1(2.2 cu ft) |
11.21 (0.4 cu ft) |
Adult human excrete |
0.4 kg |
701(2.5 cu ft) |
281(1 cu ft) |
Gas yields refer to material with its natural moisture content.
For the final design of a biogas plant the use of specific literature e.g. 131, [4], [5], [6] is recommended, likewise the consultation of a biogas expert if available.
Actual production
Fertilizer production Gas
production
Number X volume per unit = volume per day Number X volume per unit
= gas per day
Example: 2 buffalo X 15 kg/day = 30 kg/day 2 x 0.540 m³/day = 1. 08 m³/day
Buffalo |
X 15 kg/day |
= |
kg/day X 0.540 m³/day = |
m³/day |
Cows |
X 10 kg/day |
= |
kg/day X 0.360 m³/day = |
m³/day |
Calves |
X 5 kg/day |
= |
kg/day X 0.200 m³/day = |
m³/day |
Pigs (50 kg) |
X 2 kg/day |
= |
kg/day X 0.180 m³/day = |
m³/day |
Horses |
X 10 kg/day |
= |
kg|day X 0.350 m³/day = |
m³/day |
Sheep |
X 2 kg/day |
= |
kg/day X 0.100 m³/day = |
m³/day |
Chickens |
X 0.18 kg/day |
= |
kg/day X 0.011 m³/day = |
m³/day |
Toilets |
X 0.4 kg/day |
= |
kg/day X 0.030 m³/day = |
m³/day |
Green material |
kg/day X 0.200 m³/day = |
m³/day |
| |
Gas and manure production per day kg/day m³/day
Does
this correspond with livestock
in 5 years?
Increased
level X kg/day =
kg/day m³/day = m³/day
Gas and manure production
potential kg/day m³/day:
Step 3: Comparison between gas volume needed and gas generation potential
Does potential gas production match requirements? |
If so, the chosen size of plant is correct, and the next step can begin. |
Is production greater than required? |
It may be a good idea to build this plant nonetheless and to ask a neighbor if he alsorequires biogas; if not, build a smaller plant. |
Is consumption higher than potential gas production? Check the following possible measures: |
- Can consumption be lowered (calculate gas requirements again)? |
|
- Can more organic material be acquired as fuel (calculate gas production again)? |
|
- Can a plant be constructed jointly with a neighbor? |
Step 4: Calculating influencing factors on the biogas plant
Temperature - fermentation period in digester
The fermentation time is an important factor in determining the size of the biogas plant and epends on the temperature in the digester. The fermentation period is defined as the time taken for material to flow through the plant from input to output. The following guide values apply to the regions stated:
30 - 40 days |
Hot, tropical plains climate: e. g. Sudan, Cameroon, Sri Lanka, Indonesia, Venezuela,Central America |
40 - 60 days |
Hot regions which cool down only slightly in winter: e. g. India, Thailand, Philippines, Kenya, Ethiopia60 - 90 days More temperate climate with distinct drop in temperature during winter: e. g. China,Korea, Turkey |
The table below shows the relationship between material fermentation time, temperature and gas output.
In regions with a distinct winter season or severe differences between daytime and nighttime, temperatures (mountainous regions) assume a temperature 5 °C lower for calculation purposes.
Digester pit temperature ºC
Fermentation period days
Quantity of material added
The material must be added in the form of a free-flowing liquid, or else blockages will occur, However, if it is diluted too much, gas production will be reduced.
Generally speaking, the solid material must be mixed with at least the same volume of water.
An accurate calculation depends on the analysis of the material and should be based on the list shown below.
Typical mixing ratios
Cow dung, fresh: water |
1:0.5 |
Cow dung, superficially dry: water |
1:1 |
Horse and sheep's dung: water |
1:1 |
Green refuse: water |
1:0.5 to 1:2 |
Quantity of material added per day:
Type of manure/material |
Quantity (kg = 1) |
Water (kg = 1) |
Liters |
Cow dung |
+ |
= | |
Pig dung |
+ |
= | |
Other animal faeces |
+ |
= | |
Human excrete from toilets |
+ |
= | |
Agricultural refuse |
+ |
= | |
|
Volume added per day |
liters |
note: in case of concrete stable floor the collected urine is sufficient for dilation, no water needs to be added
Step 5: Establishing the dimensions of the biogas plant
Establishing the dimensions of the biogas plant
The volume of
the digester pit is determined from the volume of material added per day
multiplied by the
fermentation time.
Volume of material added per day X
fermentation time =
|
kg/day X |
days = |
|
(1000 l = 1 m³) | |
Gas volume from plant per day: |
m³/day |
|
Size of gas holder = approx. 1/2 of daily gas production = |
m³ | |
About
With the steady increase in demand for the useful exploitation of renewable energy resources the transformation of biogas into shaft - or electrical power appears as one of the sensible options for biogas utilization.
This book wants to provide a source of information not only for the various technical aspects of modification of internal combustion engines, both Diesel- and Gasoline (Otto-)engines, to operate on biogas-fuel but also for planning and economic operation of these engines in a system comprising of the fuel generating biogas plant and the power consuming driven equipment.
The reader, who is assumed to have basic technical interest and understanding, will furthermore find information on the use of the engine's waste heat and a commented list of manufacturers of biogas engines and available equipment for the self-modification of engines.
Deutsches Zentrum für Entwicklungstechnologien
ISBN
3-528-02032-6