Technique: pasted on solid ceiling
Practising of mosaic parquetry laying
Material
Mosaic parquetry-fillets, parquetry adhesive, adhesive thinner
Figure
 
Tools
Hand saw, hammer, plane, broom, pushing and drawing scrapers
Measuring and testing means
Try square, flat square, folding rule, pencil, water-level, pipe-level
Auxiliary accessories
Bucket, string, steel bolts, knee pad
Required basic knowledge
Scribing, sawing, adhesive processing, laying of building components along a string, jointing
Explanations to the working drawing
1 subfloor, 2 adhesive bed, 3 mosaic parquetry, 4 string, 5 distance to the wall, 6 steel bolt, 7 1st laying direction, 8 2nd laying direction
| Sequence of operations | Comments | 
| 1. Checking the subfloor for strength, moisture content and horizontal surface. | Subfloor must be free of cracks, firm, retain a constant volume
and be dry. | 
| 2. Taking small parquetry-fillets, as many as required (vis. instruction example 1), and transporting them to the place of use, | Faulty fillets are sorted out, processing losses have to be considered. | 
| 3. Drawing off adhesive and thinner and transporting them to the place of use. | Attention! | 
| 4. Preparing tools and auxiliary accessories and arranging the working place. | Make sure that the equipment is complete. | 
| 5. Cleaning the subfloor with broom, if necessary with pushing scraper; removing the dirt. |  | 
| 6. Preparing primary coat and spreading it. | Primary coat is made from thinned adhesive and is applied by
sectors, evenly and over the entire surface of each sector by a drawing
scraper. | 
| 7. Distributing the small parquetry-fillets and putting up a
string for alignment. | Pay attention to the angles and to parallelism. | 
| 8. Spreading the adhesive with the drawing scraper and putting the small parquetry-fillets on the adhesive coat by sectors. Pressing the fillets on firmly and accurately along the string and fixing them by slight hammer blows. | When laying the fillets, observe the intended pattern. Be
absolutely accurate along the alignment string. | 
| 9. Cleaning the working place. | Remove replaced fillets etc., clean the tools, close vessels and
take all this out of the room. | 
Mosaic
parquetry-fillets