Figure
This section provides:
· a brief introduction to the common problems of slope instability, and ways of solving them;
· a straightforward procedure to identify and implement the appropriate treatments for each site, following a series of logical steps summarised in Figure 1.3, on page 14.
Ideally, the causes of slope instability would be well understood and appropriate solutions would be easy to select. However, this is rarely the case and engineers must make assumptions about the causes of slope instability, based on their knowledge and experience of the terrain. This is particularly true in Nepal, where slopes tend to be long and steep, and the climatic variables are as yet poorly understood. Attaining a desired factor of safety may not be feasible.
With such a variety of materials and sites, choosing stabilisation techniques is a complicated process. There are many variables, most of which cannot practicably be measured in the field. Therefore, it is not possible to set quantitative limits on many of the parameters. This section outlines instead a practical analysis to help the engineer to decide on the best course of action.
Bio-engineering is not a substitute for civil engineering. It offers engineers a set of tools to complement those already available in solving a range of shallow slope problems.
Bio-engineering serves two distinct roles: providing additional techniques for stabilising shallow failures and controlling erosion; and enhancing civil engineering structures by protecting them and maximising their effectiveness. In both roles, bio-engineering techniques must be carefully integrated with civil engineering structures.
Every slope has a different variety of erosion and failure processes at work on it; often, there will be more than one process affecting each part of a slope. Freshly prepared slopes (i.e. those just cut or filled) are usually subject to erosion, and so all slopes need to be stabilised. These erosion and failure processes must be identified before remedial work can be started. Examples of the most common problems are given in Figure 1.11.
1 For a more comprehensive list of the common forms of failure and erosion, refer to pages 12 and 13 of TRL Overseas Road Note 16, Principles of low cost engineering in mountainous regions.
Shoulder erosion threatening the
edge of the road pavement. Even the smallest slope problems must be tackled
A deep planar slide on the Arniko
Highway has removed a portion of the road
Figure 1.1: Common types of erosion and slope failure
DESCRIPTION |
DEPTH |
MECHANISM* |
FUNCTION REQUIRED |
Rills and gullies form in weak, unprotected surfaces. Erosion should also be expected on bare or freshly prepared slopes. |
Usually in the top 0.5 metre, but can become deeper if not controlled. |
Erosion on the surface. |
Armour, Reinforce, Catch. |
Mass slope failure on a shallow slip plane parallel to the surface. This is the most common type of landslide, slip or debris fall. The plane of failure is usually visible but may not be straight, depending on site conditions. It may occur on any scale. |
Frequently 0.5 metres or less below surface (or along a local discontinuity). |
Planar sliding (translational landslide or debris slide). |
Reinforce, Anchor, Catch, Drain. |
Mass slope failure on a deep, curved slip plane. Many small, deep landslides are the result of this process. Large areas of subsidence may also be due to these. |
Usually > 1.5 metres deep. |
Shear failure (rotational landslide). |
Anchor, Support, Drain. |
Slumping or flow where material is poorly drained or has low cohesion between particles and liquefaction is reached. These sometimes look similar to planar slides, but are due to flow rather than sliding. The resulting debris normally has a rounded profile. |
Frequently 0.5 metres or less below surface. |
Slumping or flow of material when very wet. |
Drain, Reinforce. |
Collapse due to failure of the supporting material. This usually takes the form of a rock fall where a weaker band of material has eroded to undermine a harder band above. These are very common in mixed Churia strata. |
0.5 to 2 metres in road cuts; deeper in natural cliffs. |
Debris fall or collapse. |
Reinforce, Support. |
* The mechanisms of failure or erosion are covered in detail in the Reference Manual.
Figure 1.2: The main engineering functions of structures, with examples of techniques
FUNCTION* |
CIVIL ENGINEERING TECHNIQUE |
BIO-ENGINEERING TECHNIQUE |
COMBINATION OF BOTH |
Catch |
Catch walls |
Contour grass lines or brush layers |
Catch wall with densely planted shrubs |
|
Catch fences |
Shrubs and large bamboo clumps |
Catch wall with bamboo clumps planted above |
Armour |
Revetments |
Mixed plant storeys giving complete cover |
Vegetated stone pitching |
|
Surface rendering |
Grass carpet |
jute netting with planted grass |
Reinforce |
Reinforced earth |
Densely rooting grasses, shrubs and trees |
Wire bolster cylinders and planted shrubs or trees |
|
Soil nailing |
Most vegetation structures |
Jute netting with planted grass |
Anchor |
Rock anchors |
Deeply rooting trees |
Combination of soil anchors and deeply |
|
Soil anchors |
|
rooting trees |
Support |
Retaining walls |
Large trees and large bamboo clumps |
Retaining wall with a line of large bamboo clumps |
|
Prop walls | |
planted above |
Drain |
Masonry surface drains |
Downslope and diagonal vegetation lines |
Herringbone-pattern wire bolster cylinders and angled grass lines |
|
Gabion and french drains |
Angled fascines or brush layers |
French drains and angled grass lines |
* The six main engineering functions are defined in Section 1.2 below and are elaborated in the Reference Manual.
Figure 1.3: Flow chart to show the
progression of the steps for slope stabilisation
Figure 1.2 shows examples of civil and bio-engineering techniques that have been devised to overcome these common problems.
In the steps outlined below and shown schematically by the flow chart in Figure 1.3 on page 14, the engineer follows a logical procedure to plan and implement the works.
These steps initially use as their basis the six main functions of both civil engineering and bio-engineering techniques of slope stabilisation, given in Figure 1.2. In more detail, engineering structures serve to:
Catch eroded material moving down the slope. Movement may occur as a result of gravity alone, or with the aid of water as well. Material is caught by a physical barrier such as a wall or the stems of vegetation;
Armour the slope against erosion from runoff and rain splash. This is most effectively done using a continuous cover of low vegetation (inert coverings such as stone pitching tend to be expensive over large areas). Partial armouring is often provided, for example by using lines of grasses, brush layers or wire bolsters;
Reinforce the soil by physically stiffening it to increase its resistance to shear. Plant roots are effective at reinforcing soil;
Anchor surface material to deeper layers by soil pinning. This helps to reduce mass movements at depths greater than provided by general reinforcement. The roots of large plants emulate soil anchors or rock bolts;
Support a soil mass by buttressing. On a large scale, a retaining wall or the roots of large plants (and their stems once they have caught some debris) such as big bamboo clumps can buttress a soil mass. On a micro scale individual large stones or smaller vegetation perform this function.
Drain excess water from the slope. Drier materials tend to be more stable than wetter ones -many failures occur when the material reaches a point of liquefaction. Standard civil engineering drains can be provided; vegetation planted in lines angled down the slope help to drain the surface layers.
Sites are assessed using a standard procedure. The choice of stabilisation techniques (both standard civil and bio-engineering) depends on an identification of the functions needed to stabilise and protect the slope. These steps lead through the process to give a logical application of the techniques available.
To implement slope stabilisation works including both civil and bio-engineering, follow these steps.
Figure 1.4: Summary calendar of
civil and bio-engineering
works
Early in the fiscal year, you must prepare for the process of checking all slopes along the road and planning the year's work. The calendar in Figure 1.4 shows how the various steps involved, as described above, will be scheduled through the year.
Note that there are three critical points on this calendar; all are governed by seasons. These are:
· seed collection, which starts in Mangsir for many species;
· civil engineering works, which must be complete before the rains start in Jestha; and
· site planting, which usually starts in late Jestha or Ashad, as soon as the rains are reliable.
All of the other activities must be completed on schedule for these to be carried out in the right season. This accounts for the heavy planning and design load early in the fiscal year.
Inspect the road and make a list of the sites that require treatment. Prioritise them according to the importance of stabilisation.
Weighing the seriousness of the existing or potential failure against the damage it could cause helps to prioritise and schedule works. Figure 1.5 shows the priority to be given to different slope movement problems. The scale goes from a distinct threat to human life (e.g. houses might be lost or the entire road could be carried away) to the situation where a slope problem can cause only limited damage (e.g. occasional blocking of drains), and where treatment is more of a preventative measure (see Figure 1.5).
In many cases, budget constraints allow only the higher priority sites to be addressed. Sites up to priority 3 should always be treated if at all possible. However, the aim should be to move towards treatment of all sites under a regular maintenance programme.
Figure 1.5: Prioritisation of repair work (from the perspective of the Department of Roads)
EXPECTED CONSEQUENCE IF THE SITE IS NOT TREATED |
PRIORITY RATING |
Slope movement threatens houses |
Priority 1 (i.e. very high priority) |
Slope movement threatens complete loss of road |
Priority 2 |
Slope movement threatens partial loss of road |
Priority 3 |
Slope movement threatens complete road blockage |
Priority 3 |
Debris may fall on top of pedestrians or vehicles and cause injury |
Priority 3 |
Slope movement threatens loss of productive farmland |
Priority 4 |
Slope movement threatens blockage of drains |
Priority 4 |
Figure 1.6: Typical slope
segments, showing patterns of material
movement
A slope segment can be defined as a length of slope with a uniform angle and homogeneous material that is likely to erode or fail in a uniform manner.
The mechanical, hydrological and biological processes at work in a slope are many and complex. Nevertheless, before any remedial work can begin, it is necessary to identify the major factors contributing to instability in order to decide on appropriate action. The assessment and treatment of each site is based on the use of one or more techniques for each segment. So it is necessary to divide the slope into its component segments. Some common examples of slopes are given in Figure 1.6.
While carrying out this step on site, it is useful to sketch the site on the pro forma given in Annex A.
Before proceeding to Step 4, you should have a good knowledge of the site. You should know how many segments make up the slope, and have an idea of how the main processes at work within each segment contribute to the overall instability of the site.
From now on, each segment of slope must be considered a separate entity for treatment: both civil engineering and bio-engineering techniques should be planned for each segment rather than for an entire site.
Careful site inspection Is
essential for successful stabilisation
Figure 1.7: Common types of erosion and slope failure
MECHANISM* |
DESCRIPTION |
DEPTH |
Erosion on the surface. |
Rills and gullies form in weak, unprotected surfaces. Erosion should also be expected on bare or freshly prepared slopes. |
Usually in the top 0.1 metre, but can become deeper if not controlled. |
Gully erosion |
Gullies that are established in the slope continue to develop and grow bigger. Large gullies often have small landslides along the sides. |
Usually in the top 0.5 metre, but can become deeper if not controlled. |
Planar sliding (translational landslide or debris slide). |
Mass slope failure on a shallow slip plane parallel to the surface. This is the most common type of landslide, slip or debris fall. The plane of failure is usually visible but may not be straight, depending on site conditions. It may occur on any scale. |
Frequently 0.5 metre or less below surface (or along a local discontinuity). |
Shear failure (rotational landslide). |
Mass slope failure on a deep, curved slip plane. Many small, deep landslides are the result of this process. Large areas of subsidence may also be due to these. |
Usually > 1.5 metres deep. |
Slumping or flow of material when very wet. |
Slumping or flow where material is poorly drained or has low cohesion between particles and liquefaction is reached. These sometimes appear afterwards like planar slides, but are due to flow rather than sliding. The resulting debris normally has a rounded profile. |
Frequently 0.5 metre or less below surface. |
Debris fall or collapse. |
Collapse due to failure of the supporting material. This normally takes the form of a rock fall where a weaker band of material has eroded to undermine a harder band above. These are very common in mixed Churia strata. |
0.5 to 2 metres in road cuts; deeper in natural cliffs. |
Debris flow |
In gullies and small, steep river channels (bed gradient usually more than 15°), debris flows can occur following intensive rain storms. This takes the form of a rapid but viscous flow of liquefied mud and debris. |
The flow depth is usually 1 to 2 metres deep. |
* The mechanisms of failure or erosion are covered in detail in the Reference Manual.
This is the most important step, and the one on which you must spend the most time. You must make a site visit, and you will need:
· either some copies of the pro forma in Annex A or a notebook;· a 30-metre tape measure;
· a clinometer or an Abney level (if you do not have one of these, take this handbook with you and use the angled slope lines in Annex A to estimate slope angle in profile); and
· an altimeter, or maps or site drawings of the roadline that show the altitude.
Carefully assessing a site, through an investigation on the ground, is the key to applying good engineering practice. Without proper investigation and assessment, both civil and bio-engineering techniques are likely to fail. This section gives only a very brief guide; more details on site assessment are provided in Section 2 of the Reference Manual.
The objective of Step 4 is to arrive at a more detailed appreciation of the factors contributing to instability within each slope segment. In order to achieve this, you will need to look carefully at each segment of the site and note down the following facts (more details are given in the paragraphs below).
Erosion and failure processes |
List |
Other factors |
List |
Slope angle(s) |
3 classes: <30º, 30-45º, or>45º |
Slope length |
2 classes: 15 metres or>15 metres |
Material drainage |
2 classes: good or poor |
Site moisture |
4 classes: wet, moist, dry or very dry |
Altitude |
Determine: use an altimeter, map site drawing |
Figure 1.8: The main physical factors affecting slopes
POTENTIAL FACTOR |
DESCRIPTION |
Fault lines |
Small fault lines may cause differential erosion in parts of the site. |
Springs |
There may be seasonal springs within the site, which cause localised problems of drainage or slumping. |
Slip planes |
The main plane of failure may not be the only one. Many sites have secondary, smaller slip planes additional to the main failure mechanism |
Large gullies |
Large gullies nearby may erode backwards and damage the site. Alternatively, they may discharge, causing deposition on the site. |
Landslides |
Nearby landslides may extend headwards or sideways, or may supply debris on to the site. |
River flooding |
A large river below the site may flood badly, damaging the site by either erosion or deposition, or a combination of both. |
River cutting |
Rivers below the site may move in floods, undercutting the toe of the site. |
Catchments |
If there is an extended catchment area above the site, it could lead to a large discharge, which causes bad damage by erosion or deposition. |
Drain discharge |
The discharge of drainage water must be safeguarded to avoid causing erosion or mass failures. Poorly sited or inadequately protected discharge points can cause severe problems. |
Khet and kulo |
Khet (rice paddy) land or a kulo (irrigation channel) above a site usually means a large volume of water infiltrating into the slope, with a greater potential for failure or large-scale erosion. |
Construction activities |
Construction activities on or near the site may lead to undermining through excavations, or surcharging through spoil disposal in the wrong places. |
Erosion and failure processes
Each site has a different variety of erosion processes at work, which must be identified before remedial work can be started; often, there will be more than one process affecting each slope segment. A list of the erosion and failure problems is given in Figure 1.7. But remember that most sites, however small, are the result of a combination of these processes. It is assumed that freshly prepared slopes (i.e. those just cut or filled) are subject to erosion, and so all slopes need to be treated1.
1 For a more comprehensive list of the common forms of failure and erosion, refer to pages 12 and 13 of TRL Overseas Road Note 16, Principles of low cost engineering in mountainous regions.
List the erosion and failure processes at work in each segment of slope and mentally crosscheck it against the functions required of the stabilisation measures. Sketch these on paper for your later reference and to help with the design of structures. If you need more details on any aspect of site assessment, refer to Section 2 of the Reference Manual.
Other factors
You must identify and note down all of the physical factors affecting a site. Those additional to the basic features of slope segments are listed in Figure 1.8. Some are internal (e.g. springs) while others are external (e.g. river undercutting).
Slope angle(s)
Record the slope angles and assign each segment to one of three classes: <30°, 30 - 45°, or > 45° Slopes of less than 30° will need only mild treatment;) those falling in the other two classes will require more substantial stabilisation.
Figure 1.9: Common characteristics of well-drained and poorly drained soils
MATERIAL DRAINAGE |
TENDENCY TOWARDS GOOD DRAINAGE |
TENDENCY TOWARDS POOR DRAINAGE |
Overall drainage |
Freely draining material; dries quickly after rain storms |
Slowly draining material; tends to remain wet for long periods after rain; behaves like firm dahi (curd) |
Soil particle size |
Coarse textures; loams and sandy soils |
Fine textures; clays and silts |
Porosity |
Large inter-connecting pores |
Small pores |
Material types |
Stony colluvial debris; fragmented rock; sandy and gravelly river deposits |
Residual soils of fine texture; debris from mud flows, slumps, etc; rato mato (red clay loam soil) |
Slope types |
Fill slopes; cut slopes in stony debris (colluvium) |
Cut slopes in original consolidated ground |
Slope length
Record the length of each segment of the site as < 15 metres or > 15 metres. A slope length of 15 metres represents a practical dividing line between 'big' and 'small' site segments. Slope segments longer than 15 metres are prone to greater risks, for example of gullying. Also, cost constraints may lead to a compromise over the desired intensity of work. Segments with very long slopes (greater than 30 metres) are singled out for special consideration in step 5 (see Figure 1.11).
Material drainage
This relates to the internal porosity of soils and the likelihood of their reaching saturation, losing cohesion and starting to flow. Materials with poor internal drainage tend to have more clay than sand. They are prone to slumping at a shallow depth (e.g. < 500 mm) if they accumulate too much moisture. In such a case, stabilisation requires some kind of drainage in addition to other functions.
For convenience, materials need to be classed only into 'good' or 'poor' drainage. Figure 1.9 provides a guide.
Segment moisture
The moisture regime of the entire site must be considered although, in the field, this can only be estimated. In assessing sites, it is necessary to determine into which of four categories each segment falls.
Wet: |
permanently damp sites (e.g. north-facing gully sites). |
Moist: |
sites that are reasonably well shaded or moist for some other reason. |
Dry: |
generally dry sites. |
Very dry: |
sites that are very dry; these are usually quite hot as well (e.g. south-facing cut slopes at low altitudes). |
Figure 1.10 summarises the main factors and how they can be identified.
Altitude
Altitude is the main determinant of temperature in Nepal and therefore regulates the local climate to a large extent. It is necessary to know the altitude to a reasonable degree of accuracy (ideally +100 metres) when the actual species are selected for bio-engineering works.
Figure 1.10: Environmental factors indicating site moisture characteristics
SITE MOISTURE FACTOR |
TENDENCY TOWARDS DAMP SITES |
TENDENCY TOWARDS DRY SITES |
Aspect |
Facing N, NW, NE and E |
Facing S, SW, SE and W |
Altitude |
Above 1 500 metres; particularly above 1 800 metres |
Below 1 500 metres; deep river valleys surrounded by ridges |
Topographical location |
Gullies; lower slopes; moisture accumulation and seepage areas |
Upper slopes; spurs and ridges; steep rocky slopes |
Regional rain effects |
Eastern Nepal in general; the southern flanks of the Annapurna Himal |
Most of Mid Western and Far Western Nepal |
Rain shadow effect |
Sides of major ridges exposed to the monsoon rain-bearing wind |
Deep inner valleys; slopes sheltered from the monsoon by higher ridges to the south |
Stoniness and soil moisture holding capacity |
Few stones; deep loamy* and silty soils |
Materials with a high percentage volume of stones; sandy soils and gravels |
Winds |
Sites not exposed to winds |
Large river valleys and the Terai |
Dominant vegetation |
e.g. amliso, nigalo, bans, chilaune, katus, lali gurans, utis |
e.g. babiyo, khar, dhanyero, imili, kettuke, khayer, salla |
* Loam is the name given to a soil with moderate amounts of sand, silt and clay, and which is therefore intermediate in texture and best for plant growth.
Figure 1.11: Assessing the requirements for civil engineering treatments
QUESTION |
FUNCTIONAL IMPLICATION |
ACTION IF THE |
USE OF BIO- |
Is the slope segment or the whole site subject to a deep-seated (>1 metre depth) shear (rotational) failure? |
Major reinforcing, anchoring or physical support required. |
If the failure plane can be identified, use conventional civil retaining walls to support the toe. Alternatively, it may be possible to remove weight from higher up on the slope by heavy trimming. |
Bio-engineering measures will mainly be used to armour backfill and foundation areas. If trimming is carried out, bio-engineering measures will be needed to armour the new bare surfaces. |
Is the slope segment very long (greater than about 30 metres), steep and in danger of a mass failure below the surface? |
Reinforcing or physical support is required. Armouring is also required. Bio-engineering measures alone may be adequate, but where a large volume of surface runoff is possible, physical structures are also necessary. |
If suitable foundations are available, use retaining walls to break the slope into smaller, more stable lengths. Some other kind of physical scour check should be used, such as wire bolster cylinders. |
Bio-engineering measures must be designed to reinforce and armour the slope between the physical structures. |
Is the foot of the slope undermined, threatening higher segments or the whole Slope above? |
Strong physical support is required. Bio-engineering measures will enhance civil structures. |
Investigate the necessity of building revetment, toe or prop walls. |
Bio-engineering measures will mainly be used to armour backfill and foundation areas. |
Is there a distinct overhang or are there large boulders poorly supported by a soft, eroding band? |
Localised physical support or anchoring are required. Support can be given using a civil structure. |
Consider prop walls or dentition to support the overhang. |
The direct seeding of shrubs on fragmented rocky slopes can provide anchorage. |
Does the slope segment have a rough surface; or is it covered in loose debris; or is it a fractured rocky slope; or does it have any very steep or overhanging sections, however small? |
Armouring is required, but only after the slope has been altered to stop it shedding loose material. |
Trim the slope as far as possible to attain a smooth, clean surface with a straight profile in cross-section. |
The trimmed slope will need to be armoured afterwards by the appropriate bio-engineering measure. |
Is there water seepage, a spring or groundwater on the site, or a danger of mass slumping after heavy rain? |
Deep drainage is required. |
Investigate the need for a drainage system involving french or other sub-surface drains, depending on site conditions. |
Deep drains can be enhanced by surface bio-engineering systems (e.g. downslope planted grass lines). |
Is the slope made up of poorly drained material, with a high clay content? |
Techniques used on this sort of material must be designed to drain rather than accumulate moisture. |
There is a danger of shallow slumping. Investigate the need for a surface drainage system. |
An appropriate bio-engineering system (e.g. downslope planted grass lines) is often adequate on its own. |
Is the site a major gully, subject to occasional erosive torrents of water? |
Major drainage is already present; heavy armouring is required. |
Use masonry check dams to reduce the scouring effect. |
Between the check dams, use large bamboo planting, live check dams or vegetated stone pitching. |
At this stage, standard civil engineering structures (e.g. gabion and other types of retaining structures, breast walls, prop walls and revetments; check dams; masonry drainage systems) should be considered. In later stages, small-scale civil engineering structures used only for surface protection (i.e. stone pitching and jute netting) are considered as options where appropriate.
Some sites will not require the building of structures, but will instead be stabilised using only bio-engineering techniques. In most cases, however, bio-engineering techniques will also be employed to enhance the effectiveness of civil engineering structures. The series of questions in Figure 1.11 helps to simplify the process of assessing the requirements for major civil engineering treatments. These must be integrated with bio-engineering measures, but normally need to be implemented first.
If civil engineering structures are to be used, they must be designed and constructed according to normal practice. Apart from the key design details referred to in Section 2, these are beyond the scope of this manual. A useful reference work is TRL Overseas Road Note 16, Principles of low cost road engineering in mountainous terrain.
The next step concentrates on shallow (< 500 mm depth) stabilisation and surface protection using bio-engineering techniques, and on areas around civil engineering structures.
How to use the flow chart in Figure 1:12 There are two methods: either 1. Use it as a prescriptive system to determine the treatments required, based on the site assessment described in step 4; or 2. If you have already determined a treatment, use it to check that your choice is suitable against normal practice. |
Having completed step 5, any deeper-seated problems will have been addressed by conventional civil engineering measures, such as retaining walls and drainage systems. This step gives details of bio-engineering and other related techniques for protecting the surface, stabilising the upper 500 mm, and improving surface drainage; and for enhancing and protecting large civil engineering structures. These are required as part of the whole stabilisation package; bio-engineering must be fully integrated with any civil engineering structures.
The flowchart in Figure 1.12 suggests appropriate techniques for different slope segments. It is assumed that these are combined with appropriate civil engineering structures where necessary to enhance slope stability. Many factors determine the optimum technique or combination of techniques, but only the most important have been included here.
The seven columns in Figure 1.12, (a) to (g), are summarised below.
(a) Slope angle(s)
3 classes: <30º, 30 -
45°, or >45° (measured in step 4).
(b) Slope length
2 classes: <15 metres or >15
metres (measured in step 4).
(c) Material drainage
2 classes: good or poor
(estimated in step 4).
(d) Site moisture
2 classes: wet/moist or dry/very dry
(combined from the four estimated in step 4)1.
1 The four classes determined in step 4 (as well as the altitude of the site) are required to establish the actual species to be used for bio-engineering, in step 8.
(e) Potential problems
The potential problems to be
encountered on each slope segment have been identified in step 4.
(f) Function required
Once you have assessed the most
likely potential problems on a slope segment you can select the most appropriate
engineering functions required (i.e. catch, armour, reinforce, anchor,
support or drain) for each segment. In bio-engineering, the functions required
by the treatment determine the plant types used and the way they are propagated.
This is given in detail in step 8.
Figure 1.12: Choosing a bio-engineering technique
START (a) |
®(b) |
®
(c) |
®
(d) |
®
(e) |
®(f) |
®
(g) |
> 45° |
> 15 |
Good |
Damp |
Erosion slumping |
Armour, reinforce drain |
Diagonal grass lines |
| | |
Dry |
Erosion |
Armour, reinforce |
Contour grass lines |
| |
Poor |
Damp |
Slumping, erosion |
Drain, armour, reinforce |
1 Downslope grass lines and vegetated stone pitched rills
or |
| |
|
Dry |
Erosion, slumping |
Armour, reinforce dram |
Diagonal grass lines |
|
<15 |
Good |
Any |
Erosion |
Armour, reinforce |
1 Diagonal grass lines or |
| |
Poor |
Damp |
Slumping, erosion |
Drain, armour, reinforce |
1 Downslope grass lines or |
|
| |
Dry |
Erosion, slumping |
Armour reinforce drain |
1 Jute netting and randomly planted grass or |
30° - 45° |
>15 |
Good |
Any |
Erosion |
Armour, reinforce, catch |
1 Horizontal bolster cylinders and shrub/tree planting or
|
| |
Poor |
Any |
Slumping, erosion |
Dram, armour, reinforce |
1 Herringbone bolster cylinders & shrub/tree planting
or |
|
<15 |
Good |
Any |
Erosion |
Armour, reinforce, catch |
1 Brush layers of woody cuttings or |
| |
Poor |
Any |
Slumping, erosion |
Dram, armour, reinforce |
1 Diagonal grass lines or |
< 30° |
Any |
Good |
Any |
Erosion |
Armour, catch |
1 Site seeding of grass and shrub/tree planting or |
| |
Poor |
Any |
Slumping, erosion |
Drain, armour, catch |
1 Diagonal lines of grass and shrubs/trees or |
|
<15 |
Any |
Erosion |
Armour catch |
Turfing and shrub/tree planting | |
|
Base of any slope |
Planar sliding or |
Support, anchor, catch |
1 Large bamboo planting or |
Special conditions
Any * |
Any* |
Any* |
Any* |
Planar sliding, |
Reinforce, anchor |
Site seeding of shrubs/small trees |
> 30° |
Any |
Any rocky material |
Debris fall |
Reinforce, anchor |
Site seeding of shrubs/small trees | |
Any loose sand |
Good |
Any |
Erosion |
Armour |
Jute netting and randomly planted grass | |
Any rato mato |
Poor |
Any |
Erosion, slumping |
Armour, drain |
Diagonal lines of grass and shrubs/trees | |
Gullies |
Any gully |
Erosion (major) |
Armour, reinforce, catch |
1 Large bamboo planting or |
* Possible overlap with parameters described in the rows above. May be required in combination with other techniques listed on the rows above. Only the common potential problems listed in Figure 1.7 are given here. 'Any rocky material' is defined as material into which rooted plants cannot be planted, but seeds can be inserted in holes made with a steel bar. 'Any loose sand' is defined as any slope in a weak, unconsolidated sandy material. Such materials are normally river deposits of recent geological origin. 'Any rato mato' is defined as a red soil with a high clay content. It is normally of clay loam texture, and formed from prolonged weathering. It can be considered semi-lateritic. Techniques in bold type are preferred. Chevron pattern: <<<<< (like a sergeant's stripes). Herringbone pattern: ¬¬¬¬¬ (like the bones of a fish).
(g) Techniques
One or more techniques that are known
to be successful on sites for each category are given. However, the general
picture may not cover every case and so this flowchart cannot be considered to
be fully comprehensive: some local variation may be needed and this, of
course, is the reason for having an engineer on site.
Once this step has been completed, it is possible to move on to the detailed design of the works for each site.
Design the civil and bio-engineering works using normal procedures. It is more cost effective to design the works so that they are carried out in a fully integrated way. As usual, you should bear in mind the resources and budget available for the work. Make the designs as detailed as you can at this stage.
Practical design considerations for the most common civil engineering structures are given in Section 2.
Details of the design of bio-engineering works are given in Section 3.
Padang bans is a valuable small
bamboo for bio-engineering works on high-altitude
roads
It is important to select the right species for use in each bio-engineering technique. To do this there are three factors to consider: function/technique, propagation and site suitability.
Function/technique
Having worked through the previous steps, you will have determined the functions required for each slope segment and will now have identified the techniques you need to use. The most appropriate class of plant to use depends on the techniques. These are summarised in Figure 1.13, but are also shown in the table listing the main bio-engineering species (Figure 1.14).
Propagation
There are various methods of propagation appropriate for the main plant classes, but individual species can be propagated only by certain of these methods. The method of propagation to be used is often determined by the function required and the bio-engineering technique being used. For example, if grass lines are to be planted, the species chosen must be capable of propagation from slip cuttings; if brush layering, palisades or fascines are to be used, the shrubs or small trees must be capable of growing from hardwood cuttings.
Site suitability
Whatever the function and propagation method required of the plants by the bio-engineering technique, the plants selected must be able to grow in the site being treated. The suitability of each species to their growing sites is complex, but there are some straightforward rules that simplify the matter. The three main aspects of the environment affecting plant growth are as follows.
· Temperature. This is very closely related to altitude for most of Nepal. In choosing the species, therefore, the site altitude measured in step 4 is used.· Moisture. This is very difficult to quantify. It was assessed in step 4 for the site and classed as one of wet, moist, dry or very dry. This is now used to choose the species.
· Nutrients. The main species used in bio-engineering are all tolerant of very poor soils. Therefore the nutrition factor can be ignored at this stage.
The final choice of species according the technique for which it is to be used, and the site characteristics of altitude and moisture, is made by reference to Figure 1.14.
Figure 1.13: Bio-engineering techniques and appropriate plant classes
TECHNIQUES |
PLANT CLASS TO USE |
PACE REFERENCE | |
Planted grass lines (all configurations) and vegetated stone pitching gully beds |
Grasses grown from slip/rhizome cuttings |
page |
28 |
Brush layers, palisades, live check dams, fascines and vegetated stone pitching walls |
Shrubs */ small trees grown from hardwood cuttings |
page |
30 |
Large bamboo planting |
Large bamboos |
page |
33 |
Site seeding with grass |
Grasses grown from seed |
page |
29 |
Turfing |
Small sward grasses |
page |
29 |
Site seeding with shrubs/small trees |
Robust shrubs/small trees grown from seeds |
page |
32 |
Shrub/small tree planting |
Shrubs/small trees (grown from seeds/polypots) |
page |
31 |
Large tree planting |
Large trees (grown from seeds/polypots) |
page |
31 |
* A shrub is a woody plant with multiple stems growing up from the ground; a tree has usually one stem growing up from the ground. For bio-engineering purposes, shrubs and small stature trees have the same functions, since the rooting patterns tend to be similar.
Figure 1.14: Selection of species for bio-engineering by groups of techniques
Planted grass lines (all configurations) and vegetated stone
pitching gully beds
These grasses are grown from slip or rhizome cuttings
MOISTURE |
WET |
MOIST |
DRY |
VERY DRY |
ALTITUDE |
|
Grasses |
| |
2500 - 2000 m |
Padang bans |
Padang bans |
Tite nigalo bans |
|
|
Tite nigalo bans |
Phurke | |
|
| |
Tite nigalo bans |
| |
2000 - 1500 m |
Amliso |
Amliso |
Amliso |
Babiyo |
|
Kans |
Babiyo |
Babiyo |
Kans |
|
Katara khar |
Kans |
Kans |
Khar |
|
Padang bans |
Katara khar |
Katara khar |
|
|
Phurke |
Khar |
Khar | |
|
Tite nigalo bans |
Padang bans |
Phurke | |
| |
Phurke |
Tite nigalo bans |
|
| |
Tite nigalo bans |
| |
1500 - 1000 m |
Amliso |
Amliso |
Amliso |
Babiyo |
|
Kans |
Babiyo |
Babiyo |
Dhonde |
|
Katara khar |
Dhonde |
Dhonde |
Kans |
|
Khus |
Kans |
Kans |
Khar |
|
Phurke |
Katara khar |
Katara khar |
Narkat |
|
Sito |
Khar |
Khar | |
|
Tite nigalo bans |
Khus |
Khus | |
| |
Narkat |
Narkat | |
| |
Phurke |
Phurke | |
| |
Sito |
Sito | |
| |
Tite nigalo bans |
| |
1000 - 500 m |
Amliso |
Amliso |
Amliso |
Babiyo |
|
Kans |
Babiyo |
Babiyo |
Dhonde |
|
Katara khar |
Dhonde |
Dhonde |
Kans |
|
Khus |
Kans |
Kans |
Khar |
|
Phurke |
Katara khar |
Katara khar |
Narkat |
|
Sito |
Khar |
Khar | |
| |
Khus |
Khus | |
| |
Narkat |
Narkat | |
| |
Phurke |
Phurke | |
| |
Sito |
Sito | |
500 m - Terai |
Amliso |
Amliso |
Amliso |
Babiyo |
|
Kans |
Babiyo |
Babiyo |
Dhonde |
|
Katara khar |
Dhonde |
Dhonde |
Kans |
|
Khus |
Kans |
Kans |
Khar |
|
Sito |
Katara khar |
Katara khar |
Narkat |
| |
Khar |
Khar | |
| |
Khus |
Khus | |
| |
Narkat |
Narkat | |
| |
Sito |
Sito | |
This table gives the main species used for bio-engineering in Nepal. A range of plants is available for each particular location. A list of all tested bio-engineering species is given in Annex B. Full details of the main bio-engineering species are given in the Reference Manual.
Figure 1.14: Selection of species for bio-engineering by groups of techniques
Species for grass seeding and turfing
Moisture |
Wet |
Moist |
Dry |
Very dry | ||||
Altitude |
Clump grasses (for seeding) |
Small sward grass (for turfing) |
Clump grasses (for seeding) |
Small sward grass (for turfing) |
Clump grasses (for seeding) |
Small sward grass (for turfing) |
Clump grasses (for seeding) |
Small sward grass (for turfing) |
2500 - | | | | | | | | |
2000 - |
Kans |
Dubo |
Babiyo |
Dubo |
Babiyo |
Dubo |
Babiyo | |
1500 m |
Katara khar |
|
Kans | |
Kans | |
Kans | |
|
Phurke | |
Katara khar |
|
Katara khar |
|
Khar | |
| | |
Khar | |
Khar | | | |
| | |
Phurke | |
Phurke | |
| |
1500- |
Kans |
Dubo |
Babiyo |
Dubo |
Babiyo |
Dubo |
Babiyo | |
1000m |
Katara khar |
|
Dhonde | |
Dhonde | |
Dhonde | |
|
Phurke | |
Kans | |
Kans | |
Kans | |
|
Sito | |
Katara khar |
|
Katara khar |
|
Khar | |
| | |
Khar | |
Khar | | | |
| | |
Phurke | |
Phurke | |
| |
| | |
Sito | |
Sito | | | |
1000 - |
Kans |
Dubo |
Babiyo |
Dubo |
Babiyo |
Dubo |
Babiyo | |
500 m |
Katara khar |
|
Dhonde | |
Dhonde | |
Dhonde | |
|
Phurke | |
Kans | |
Kans | |
Kans | |
|
Sito | |
Katara khar |
|
Katara khar |
|
Khar | |
| | |
Khar | |
Khar | | | |
| | |
Phurke | |
Phurke | |
| |
| | |
Sito | |
Sito | | | |
500m- |
Kans |
Dubo |
Babiyo |
Dubo |
Babiyo |
Dubo |
Babiyo | |
Terai |
Katara khar |
|
Dhonde | |
Dhonde | |
Dhonde | |
|
Sito | |
Kans | |
Kans | |
Kans | |
| | |
Katara khar |
|
Katara khar |
|
Khar | |
| | |
Khar | |
Khar | | | |
| | |
Sito | |
Sito | | | |
This table gives the main species used for bio-engineering in Nepal. A range of plants is available for each particular location. A list of all tested bio-engineering species is given in Annex B. Full details of the main bio-engineering species are given in the Reference Manual.
Calculate the quantities and rates required for the works. This is a standard procedure and, for work by the Department of Roads, must follow the schedules established by the government for this purpose.
Rate analysis norms for bio-engineering are given in the Reference Manual.
You can now finalise the work to be undertaken in the year's programme. This entails determining the right balance between the resources available and the seriousness of the failures on the sites that need to be stabilised.
The prioritisation made in step 2 showed how important it is to stabilise each site. This should be re-examined to check that the higher priority sites can all be covered. In certain cases it may be necessary to return to steps 7 and 8, to reconsider the design of the civil and bio-engineering works with a view to reducing costs and covering more sites.
Figure 1.14: Selection of species for bio-engineering by groups of techniques
Species for brush layers, palisades, live check dams,
fascines and vegetated stone pitching walls
Shrubs/small trees grown from
hardwood cuttings
Moisture |
Wet |
Moist |
Dry |
Very dry | ||||
Altitude |
Shrubs/ small trees |
Large trees* |
Shrubs/ small trees |
Large trees* |
Shrubs/ small trees |
Large trees* |
Shrubs/ small trees |
Large trees* |
2500 - |
Bainsh |
Phaledo |
Bainsh |
Phaledo | |
Phaledo | |
|
2000 m |
| | |
| | |
| |
2000 - |
Bainsh |
Phaledo |
Bainsh |
Phaledo |
Namdi phul |
Phaledo | |
|
1500 m |
Namdi phul |
|
Namdi phul |
| | |
| |
1500 - |
Bainsh |
Dabdabe |
Bainsh |
Dabdabe |
Kanda phul |
Phaledo | |
|
1000 m |
Namdi phul |
Phaledo |
Kanda phul |
Phaledo |
Namdi phul |
| | |
|
Saruwa/ | |
Namdi phul |
|
Saruwa/ | |
| |
|
bihaya | |
Saruwa/ | |
bihaya | |
| |
| | |
bihaya | |
Simali | |
| |
| | |
Simali | |
| | | |
1000 - |
Assuro |
Dabdabe |
Assuro |
Dabdabe |
Assuro |
Dabdabe |
Assuro | |
500 m |
Bainsh | |
Bainsh | |
Kanda phul |
|
Kanda phul |
|
|
Kanda phul |
|
Kanda phul |
|
Saruwa/ | |
| |
|
Saruwa/ | |
Saruwa/ | |
bihaya | |
| |
|
bihaya | |
bihaya | |
Simali | |
| |
|
Simali | |
Simali | |
| | | |
500 m - |
Assuro |
Dabdabe |
Assuro |
Dabdabe |
Assuro |
Dabdabe |
Kanda phul |
|
Terai |
Bainsh | |
Bainsh | |
Kanda phul |
| | |
|
Kanda phul |
|
Kanda phul |
|
Saruwa/ | |
| |
|
Saruwa/ | |
Saruwa/ | |
bihaya | |
| |
|
bihaya | |
bihaya | |
Simali | |
| |
|
Simali | |
Simali | |
| | | |
* Required for live check dams onlyThis table gives the main species used for bio-engineering in Nepal. A range of plants is available for each particular location. A list of all tested bio-engineering species is given in Annex B. Full details of the main bio-engineering species are given in the Reference Manual.
Calculate the exact need for plants for the bio-engineering works. This can be done with reference to Section 3, which gives the plant spacings for each of the bio-engineering techniques. This will allow you to list the precise plant requirements for the programme. In turn, this is what must be produced by your nurseries, provided by the contractors or obtained from elsewhere.
It is standard practice when planning the growing of plants in a nursery to allow for losses during production. This is covered in Section 4. Therefore at this stage you should calculate the exact site needs, and you do not need to add an allowance for losses before the plants reach site. It may, however, be useful to add a contingency quantity of plants in case site conditions vary from those expected, and more plants are required.
Figure 1.14: Selection of species for bio-engineering by groups of techniques
Species for shrub/small tree planting and large tree
planting
Shrubs/small trees grown from seeds/polypots
Moisture |
Wet |
Moist |
Dry |
Very dry | ||||
Altitude |
Shrubs/ small trees |
Large trees |
Shrubs/ small trees |
Large trees |
Shrubs/ small trees |
Large trees |
Shrubs/ small trees |
Large trees |
2500 - |
|
Lankuri | |
Gobre salla |
|
Gobre salla |
|
Gobre salla |
2000 m |
|
Painyu | |
Lankuri | |
Lankuri | |
|
| |
Rato siris |
|
Rato siris |
|
Rato siris |
| |
| |
Utis | |
Utis | |
Utis | | |
2000 - |
|
Chilaune |
Keraukose |
Bakaino |
Keraukose |
Bakaino |
Keraukose |
Bakaino |
1500 m |
|
Khanyu | |
Chilaune | |
Chilaune | |
Gobre salla |
|
|
Lankuri | |
Gobre salla |
|
Gobre salla |
|
Khanyu |
| |
Painyu | |
Khanyu | |
Khanyu | |
Rani salla |
|
|
Rato siris |
|
Lankuri | |
Painyu | |
|
| |
Utis | |
Painyu | |
Rani salla |
| |
| |
| |
Rani salla |
|
Rato siris |
| |
| |
| |
Rato siris |
|
Utis | | |
| | | |
Utis | | | | |
1500 - |
Keraukose |
Chilaune |
Areri |
Bakaino |
Areri |
Bakaino |
Areri |
Bakaino |
1000 m |
|
Khanyu |
Dhanyero |
Chilaune |
Dhanyero |
Chilaune |
Dhanyero |
Khanyu |
| |
Lankuri |
Kanda phul |
Khanyu |
Kanda phul |
Khanyu |
Kanda phul |
Rani salla |
|
|
Painyu |
Keraukose |
Painyu |
Keraukose |
Painyu |
Keraukose |
|
| |
Rato siris |
Tilka |
Rani salla |
Tilka |
Rani salla |
Tilka | |
| |
Seto siris |
|
Rato siris |
|
Rato siris |
| |
| |
Utis | |
Seto siris |
| | |
|
| | |
|
Sisau | |
| | |
| |
| |
Utis | | | | |
1000 - |
Dhanyero |
Khanyu |
Areri |
Bakaino |
Areri |
Bakaino |
Areri |
Bakaino |
500 m |
Dhusun |
Painyu |
Dhanyero |
Kalo siris |
Dhanyero |
Kalo siris |
Dhanyero |
Kalo siris |
|
Keraukose |
Rato siris |
Dhusun |
Khanyu |
Dhusun |
Khanyu |
Dhusun |
Khanyu |
|
Tilka |
Seto siris |
Kanda phul |
Painyu |
Kanda phul |
Khayer |
Keraukose |
Khayer |
| |
Sisau |
Keraukose |
Rani salla |
Keraukose |
Painyu |
Tilka |
Rani salla |
|
|
Utis |
Tilka |
Seto siris |
Tilka |
Rani salla |
|
Sisau |
| | | |
Sisau | |
Sisau | |
|
500 m- |
Dhanyero |
Khanyu |
Dhanyero |
Bakaino |
Dhanyero |
Bakaino |
Dhanyero |
Bakaino |
Terai |
Dhusun |
Seto siris |
Dhusun |
Kalo siris |
Dhusun |
Kalo siris |
Dhusun |
Kalo siris |
|
Keraukose |
Sisau |
Kanda phul |
Khanyu |
Kanda phul |
Khanyu |
Keraukose |
Khanyu |
|
Tilka | |
Keraukose |
Seto siris |
Keraukose |
Khayer |
Tilka |
Khayer |
| | |
Tilka |
Sisau |
Tilka |
Sisau | |
|
This table gives the main species used for bio-engineering in Nepal. A range of plants is available for each particular location. A list of all tested bio-engineering species is given in Annex B. Full details of the main bio-engineering species are given in the Reference Manual.
In this step, the question as to whether the works are to be carried out by contract or through a direct labour force is considered. Both have advantages in different situations. Small-scale works are normally best done through daily-rated labour. Both the government regulations and the private sector in Nepal provide considerable flexibility for either system.
Whichever method of implementation is chosen, it is necessary at this stage to prepare the appropriate documentation for the works to be undertaken. For contracting, standard specifications for bio-engineering are given in the Reference Manual. Standard specifications for civil engineering structures are also available from the Department of Roads.
Figure 1.14: Selection of species for bio-engineering by groups of techniques
Species for seeding (on site) with shrubs/small trees or
large trees
Robust plants grown from seeds
Moisture |
Wet |
Moist |
Dry |
Very dry | ||||
Altitude |
Shrubs/ small trees |
Large trees |
Shrubs/ small trees |
Large trees |
Shrubs/ small trees |
Large trees |
Shrubs/ small trees |
Large trees |
2500 - |
|
Utis* | |
Gobre salla |
|
Gobre salla |
|
Gobre salla |
2000 m |
| | |
Utis* | |
Utis* | |
|
2000 - |
|
Khanyu * |
Keraukose |
Bakaino |
Keraukose |
Bakaino |
Keraukose |
Bakaino |
1500 m |
|
Utis* | |
Gobre salla |
|
Gobre salla |
|
Gobre salla |
|
| | |
Khanyu * | |
Khanyu * | |
Khanyu * |
| | | |
Rani salla |
|
Rani salla |
|
Rani salla |
|
| | |
Utis* | |
Utis* | |
|
1500 - |
Bhujetro |
Khanyu * |
Areri |
Bakaino |
Areri |
Bakaino |
Areri |
Bakaino |
1000 m |
Keraukose |
Utis * |
Bhujetro |
Khanyu * |
Bhujetro |
Khanyu * |
Bhujetro |
Khanyu * |
| | |
Keraukose |
Rani salla |
Keraukose |
Rani salla |
Keraukose |
Rani salla |
|
| | |
Sisau | |
| | |
| |
| |
Utis* | |
| | |
1000 - |
Bhujetro |
Khanyu * |
Areri |
Bakaino |
Areri |
Bakaino |
Areri |
Bakaino |
500 m |
Keraukose |
Sisau |
Bhujetro |
Kalo siris |
Bhujetro |
Khanyu * |
Bhujetro |
Khanyu * |
| |
Utis* |
Keraukose |
Khanyu * |
Keraukose |
Khayer |
Keraukose |
Khayer |
| | | |
Rani salla |
|
Rani salla |
|
Rani salla |
|
| | |
Sisau | |
Sisau | |
Sisau |
500 m - |
Keraukose |
Khanyu * |
Keraukose |
Bakaino |
Keraukose |
Bakaino |
Keraukose |
Bakaino |
Terai |
|
Sisau | |
Khanyu * | |
Khanyu * | |
Khanyu * |
| | | |
Sisau | |
Khayer | |
Khayer |
| | | | | |
Sisau | |
|
* Utis and khanyu should be seeded by broadcasting (broadcasting is where seed is thrown over the surface in as even a way as possible, but forming a totally random, loose cover) only. The other species have larger seeds and can be direct seeded (direct seeding is where seeds are sown carefully by hand into specific locations in a slope, such as in gaps between fragmented rock).This table gives the main species used for bio-engineering in Nepal. A range of plants is available for each particular location. A list of all tested bio-engineering species is given in Annex B. Full details of the main bio-engineering species are given in the Reference Manual.
There are three main considerations in producing plants.
· Seeds must be collected for the grasses, shrubs and trees that are needed for the programme (step 11). Seed collection times for bio-engineering plants are given in Annex B. The timing of this operation is critical (for obvious biological reasons) and orders must be placed in time. The calculation of the required seed quantities is given in Section 4.· Fill grass slip beds with stock to give sufficient of the right species of plants. Section 4 gives all the details of grass bed preparation and production in nurseries.
· Nurseries must be checked to make sure that they have all the resources necessary for the production season. Below about 1200 metres, nurseries should be prepared in Mangsir and Poush (mid November to mid January) for growth and production to start in Falgun (February). Section 4 provides the details for nursery preparation and production.
Higher altitude nurseries need a longer phase of production. Above about 1500 metres, and certainly above 1800 metres, most plants need to grow for a year in the nursery. Plants raised from seeds sown in Shrawan (July-August) of one year will be planted out on site in Ashad (June-July) of the following year. Nurseries between 1200 and 1800 metres must be planned on an individual basis depending on the particular local micro-climate. Some nurseries in this zone take six months and some take a year to produce usable plants.
Figure 1.14: Selection of species for bio-engineering by groups of techniques
Species for large bamboo planting
Moisture |
Wet |
Moist |
Dry |
Very dry |
Altitude |
|
Large bamboos | | |
2500 - 2000 m |
Kalo bans |
Kalo bans |
Kalo bans |
|
2000-1500 m |
Choya bans |
Choya bans |
Kalo bans |
|
|
Kalo bans |
Kalo bans |
Nibha bans |
|
|
Nibha bans |
Nibha bans |
| |
1500 - 1000 m |
Choya bans |
Choya bans |
Mal bans | |
|
Dhanu bans |
Dhanu bans |
Nibha bans |
|
|
Kalo bans |
Kalo bans |
Tharu bans |
|
|
Mal bans |
Mal bans | |
|
|
Nibha bans |
Nibha bans |
| |
|
Tharu bans |
Tharu bans |
| |
1000 - 500 m |
Choya bans |
Choya bans |
Mal bans | |
|
Dhanu bans |
Dhanu bans |
Tharu bans |
|
|
Mal bans |
Mal bans | |
|
|
Tharu bans |
Tharu bans |
| |
500 m - Terai |
Dhanu bans |
Dhanu bans |
Mal bans | |
|
Mal bans |
Mal bans |
Tharu bans |
|
|
Tharu bans |
Tharu bans |
| |
This table gives the main species used for bio-engineering in Nepal. A range of plants is available for each particular location. A list of all tested bio-engineering species is given in Annex B. Full details of the main bio-engineering species are given in the Reference Manual.
Kanda phul can be grown from
hardwood cuttings and prefers dry sites between 500 m and 1500 m altitude
The final part of the design phase involves issuing the necessary instructions for site responsibilities and quality control. Check that all staff understand the designs for every part of the site works, and that they know the implementation programme and where their responsibilities lie.
If contractors are being employed, it is also necessary to finalise the liability for defect repair if this has not already been established in the contract. It may be necessary to make special arrangements if different civil engineering works and bio-engineering contractors are being used on the same sites.
At this stage it is also necessary to check that safety measures are understood and will be complied with. See page 10 for a Safety Code of Practice for Working on Slopes.
Before civil engineering structures can be put in place and bio-engineering treatments applied, the site must be properly prepared. The surface should be clean and firm, with no loose debris. It must be trimmed to a smooth profile, with no vertical or overhanging areas. The object of trimming is to create a semi-stable slope with an even surface, as a suitable foundation for subsequent works.
Trim slopes to a straight profile, with a slope angle of between 30° and 60°. (In certain cases the angle will be steeper, but review this carefully in each case.) Never produce a pronounced convex or concave profile; these are prone to failure starting at a steep point. Trim off steep sections of slope, whether at the top or bottom. In particular, avoid convex profiles with an over-steep lower section, since a small failure at the toe can destabilise the whole slope above. Remove all small protrusions and unstable large rocks. Eradicate indentations that make the surrounding material unstable by trimming back the whole slope around them. If removing indentations would cause an unacceptably large amount of work, excavate them carefully and build a prop wall.
In plan, a trimmed slope does not need to be straight. An irregular plan view is acceptable and, in most cases, reduces costs because protrusions do not need to be removed.
Remove all debris and loose material from the slope surface and toe to an approved tipping site. If there is no toe wall, the entire finished slope must consist of undisturbed material.
Where toe walls form the lower extreme of the slopes to be trimmed, you can use the debris for backfilling. Where backfilling is practised, compact the material in layers, 100 to 150 mm thick and sloping back at about 5°, by ramming it thoroughly with tamping irons. This must be done while the material is moist.
Dispose of excess spoil carefully, in an approved tipping site. Just throwing it over the nearest valley side wall is not good enough. Much slope instability and erosion is caused in this way. Always include adequate provision in your estimates for haulage to an approved safe tipping area.
A carefully prepared site has more
chance of reaching stability
Trimming slopes
To trim slopes effectively, follow these steps.
1 Check that all prior construction work has been completed and that the site is clear of equipment.2 Define the type of site. Possibilities are as follows: minor trimming required only on part of site; keeping rill or gully pattern in plan section; trimming to a new designed plan section; new retaining wall to be backfilled.
3 Make a site visit and explain to the site staff and workers exactly what the finished site should look like. Draw sketches to ensure their understanding.
4 Ensure that there is safe access to the site. On very steep slopes, make new paths if necessary. Make sure that ropes or ladders are provided. When trimming a site, always work from the top of the site, moving down the slope. Check that all safety requirements have been fulfilled (refer to the section on safety in the Introduction, pages 10 and 11).
5 Carry out a trimming survey. Put in pegs and lines as necessary.
6 Cut notches through the mass to be trimmed to give the final cut lines.
7 Trim in steps from the top, using the steps as ledges for the labourers to stand on during trimming.
8 If backfilling is required behind a retaining structure below, compact the trimmed material as you go. This will require halting the trimming, redistributing and compacting the debris as backfill. Compact in level layers approximately 100 - 150 mm thick, laid back into the slope at about 5°. If possible, add water while compacting the material.
9 Complete the main trim. Then go back to the top of the slope and work down again, carrying out the final trim. This should give a clean, smooth surface, good enough for vegetation to be planted on.
10 Check the final trim line. If protrusions or indentations remain, go back and re-do those parts; if the profile is satisfactory, clean all debris off the slope finally and tidy up.
11 Dispose of excess spoil safely (see below).
Trimming should be done
logically, to remove as much or as little as necessary. On this slope, the
weaker material has been trimmed ready for grass planting, while a hard rock
outcrop has been left intact
Spoil disposal
However much care is taken to minimise quantities of spoil, it cannot be eliminated altogether. Controlling the disposal of spoil is very important, because it can give rise to a variety of problems, including:
· erosion of the spoil tip itself;· the smothering or removal of natural vegetation. Once stripped of plant and soil cover, slopes usually take three to five years to re-vegetate, and as many as 10 years on steeper and more sterile slopes;
· instability within the spoil material itself, especially when infiltrated by water;
· overloading and resultant failure of the slope;
· disruption of existing runoff patterns and siltation of water courses and drainage channels;
· disruption to agricultural practices.
Even on valley alignments, spoil
tipping must be carefully controlled. This debris should have been pushed down
to the river; left like this, it surcharged the slope and contributed to a
slide
You can minimise spoil problems by taking two steps. The first is to identify those operations that will generate spoil, the places where it will be generated and the quantities involved, no matter how small. The second is to plan for its disposal by designating safe tipping sites.
You are responsible for designating suitable sites, and your criteria for their selection should aim to avoid the problems listed above. When construction is being undertaken through a conventional construction contract, you should ensure that both the contractor and the construction workforce are aware of the restrictions on the disposal of spoil, the location of approved spoil disposal sites and specific requirements for the management of these sites. Strictly enforce contract specifications regarding spoil disposal.
You may choose either to discard spoil, or to turn it into landfill. Observe the following guidelines:
· when you are creating a landfill site, make maximum use of terraces, level ground and spurs;· if spoil tipping has to be done on steep slopes, select areas formed in resistant bedrock. Tipping should result in no more than the removal of vegetation and shallow soil, with negligible slope incision thereafter. Bitumen drum disposal chutes can be used to convey the spoil down a short slope to a safe site below;
· build many small spoil benches rather than a few large ones, to avoid slope overloading;
· provide a drainage blanket beneath a spoil bench where there is any indication of a spring seepage at or near the spoil site;
· compact spoil benches during construction. While benches cannot be compacted in the formal sense, you can construct them in definite lifts normally not more than 0.5 m thick, with the top surface of each lift approximately horizontal. This will allow machines involved in spreading the spoil to track the surface and provide some degree of compaction;
· where spoil benches are constructed on agricultural land, form the tip into a benched profile so that it can eventually be returned to agricultural production. In the meantime, the risers between levels must be protected against erosion by applying vegetation or constructing dry stone walls;
· where the top surface of the bench is large, reduce runoff by providing regular shallow interceptor drains. The slope of these drains should be constant as far as is practicable and should not be so steep as to induce erosion;
· on completion, leave spoil benches in their required shape and plant them with grasses, shrubs and trees to encourage maximum stability and resistance to erosion.
Do not permit the following:
· tipping of spoil into stream channels other than major rivers, as the increased sediment load will lead to scour and siltation downstream;· tipping of spoil on to slopes where road alignments, housing areas or farmland downslope might be affected;
· use of areas of past or active instability and erosion as tip sites, unless they are at least 50 metres from the road;
· the discharge of runoff over the loose front edge of a tip bench during or after construction;
· tipping of spoil in front of road retaining walls, where impeded drainage could soften the wall foundation.
Careless spoil disposal on long,
steep slopes can cause very extensive damage
Figure 1.15: Checklist to assess the quality of bio-engineering site works
TYPE OF WORKS |
SIGNS OF GOOD WORKS |
Individual plants |
A bright, healthy colour. |
|
Showing no signs of wilting. |
|
Well proportioned (i.e. not stunted or very tall and thin). |
|
Crowing fast, with a number of long new shoots. |
|
Without signs of discoloration on the leaves. |
|
Without signs of insect attack on the leaves or shoots (e.g. holes eaten in the leaves). |
|
Without any obvious signs of disease. |
|
Undamaged. |
|
Not yellowed, except in the later part of the dry season. |
Whole sites |
Completely treated, with no gaps or areas missed out. |
|
Evenly covered. |
|
Fully tidied up, with no loose debris on the slope. |
|
Showing no signs of instability. |
|
Stable enough to survive the early rains while plants get established. |
|
Generally looking good, complete and healthy throughout. |
Grass lines |
Complete, with plants at the spacing specified within the rows. |
|
The right distance between the rows, according to specification. |
|
Even, with no gaps or poor plants in them. |
|
Straight, according to specification. |
Brush layers and palisades |
Complete, with the right number of cuttings per running metre. |
|
The right distance between the lines, according to specification. |
|
Even, with no gaps or dead cuttings. |
|
Straight, according to specification. |
Fascines |
Complete, with the right number of cuttings per running metre. |
|
The right distance between lines, according to specification. |
|
Straight, according to specification. |
Dressing stone during the
construction of dry stone dentition
Civil engineering works must be completed before the start of the rainy season. This usually disrupts work seriously from Jestha (May-June) onwards. Hence the calendar in Figure 1.4 (step 15) suggests carrying out site preparation works in Magh (January-February), and implementing the civil engineering works between Falgun and Baisakh (mid February to mid May).
All works must be carried out to a high standard. For this it is necessary to ensure that adequate site supervision and monitoring are provided.
The actual implementation of bio-engineering site works normally begins in Ashad (late June). However, this depends on the onset of reliable monsoon rains. In the east of Nepal it may be slightly earlier, perhaps even in Jestha; and in the far west a little later, perhaps not until the second half of Ashad. The start should usually coincide with the time when farmers start to plant rice on non-irrigated khet land in the local area.
As usual, it is necessary to provide adequate site supervision to ensure that the works are carried out to the highest possible standard. Section 3 gives the construction steps for all bio-engineering techniques.
Check that the works have been completed to a high standard on the site. Figure 1.15 gives a simple checklist for assessing the quality of bio-engineering works. It is not fully comprehensive, but gives the main indicators to look for.
If the plants are being attacked by animals, or are likely to be, provide protection. Move on to step 19 to plan the maintenance inputs required by each site.
Grass planting on an eroded
landslide scar. The supervisor is monitoring the works
closely
The maintenance of bio-engineering sites is part of roadside support maintenance. This is split between routine and preventative maintenance activities.
The maintenance of roadside vegetation should be planned to ensure that maximum benefit is attained from the existing infrastructure. Most maintenance activities have to be carried out at a specific time of year. You should consider each site independently because maintenance interventions are site-specific for each slope in each roadside area.
In order to plan roadside support maintenance carefully, it is necessary to follow these steps.
(a) Devise a schedule of checks for all roadside support maintenance activities (i.e. list the maintenance tasks and the intervention times).(b) Devise a schedule of sites for each check.
(c) Carry out the checks punctually at the allotted times for every selected area.
(d) Monitor the programme to ensure that the maintenance takes place as required.
The calendar in Figure 1.16 summarises the timing for the recommended bio-engineering maintenance operations. (Full details of bio-engineering maintenance are given in Section 5.)
WHERE TO FIND MORE INFORMATION
In this site handbook, more information is given on each step. However, because of the large amount of information, the handbook is split up into a series of technical sections from this point on. The main sections are as follows.
Section 2 Civil engineering techniques: design features of the main civil engineering works and construction details of the smaller scale techniques not covered by other manuals.
Section 3 Bio-engineering techniques: construction details of all the bio-engineering techniques used by the Department of Roads.
Section 4 Plant production and nurseries: full practical information about the propagation of plants for bio-engineering and the management of nurseries.
Section 5 Maintenance of bio-engineering sites: practical guidelines on every maintenance task under routine and preventative off-road (or roadside support) maintenance related to vegetation.
In addition, the Reference Manual contains a great deal of supporting information.
Figure 1.16: Calendar of
bio-engineering maintenance
operations