The main objective of any plant owner/user is to have a well-functioning biogas plant that involves a modest amount of work for operating it and requires very little effort and expense for maintenance and repair in the long run. Smooth running of a biogas plant is dependent on good information and careful planning and construction. Operating errors and false expectations are the most frequent causes of plant outage.
The commissioning procedure for a biogas plant includes:
-
inspection and final acceptance of all components
- initial filling
-
starting the plant
- user familiarization
Inspection and final acceptance
Prior to filing the plant, all components must be carefully inspected for proper function and suitability for acceptance. Of particular importance at the time of final acceptance is seal testing of the digester, gasholder and gas pipes.
It must be kept in mind that the seal tests described below are very laborious without pumps (e.g. hauling of more than 10 m³ water) and may not even be feasible if water is scarce, in which case such testing must be dispensed with. The time and effort involved must be weighed against the risk of having to empty the plant after completely filling it with slurry. In either case, it is very advisable to use a motor pump.
Water-seal testing
Fill the entire digester with water and
check the fill level in all components.
Once all components have become saturated with water (after about 1 day), refill to the zero line, wait one day, and then remeasure. If the water loss amounts to less than 2% of the digester volume, the plant may be regarded as leaktight.
Seal testing (water and gas) of a fixed-dome plant
Fixed-dome
plants are regarded as leaktight if the water-seal test shows less than 2% water
loss, and the gas-seal test shows less than 5% gas loss.
Gas-seal testing of a floating-drum plant
In the case of
floating-drum plant, only the metal gasholder must be subjected to gas seal
testing; any leaks are detected with the aid of soap water.
Fig.
7.1: Water-seal testing of a digester. 1 Fill the plant with water, Check the
fill levels: 21 Inlet no water in the mixing pit, 22 Digester - at least 10 cm
neck height above water level. 3 Refill to compensate for moisture absorbed by
the masonry. 31 Mark the water level. 4 Measure the drop in water level as basis
for calculating the water loss (W1 = p r² X h). 5 Repeat measurements as
necessary. (Source: OEKOTOP)
Fig.
7.2: Seal testing (water and gas) of a fixed-dome plant. 1 Fill the plant up to
the zero line; Check the fill levels: 21 Gas extraction points at least 10 cm
above discharge level, 22 Water level in the displacement pit. 3 Perform
water-seal test and level-drop check (cf. fig. 7.1). 4 Close the entry hatch. 5
Fill with gas up to maximum a1lowable plant pressure a) with air (pump), b) with
exhaust gas (vehicle exhaust), 51 . . . until the displacement pit overflows, or
52 . . . until gas bubbles out of the inlet pipe. 6 Refill the plant to
compensate for saturation losses. 7 Measure the level drop (h) after one day,
and calculate the gas losses. (Source: OEKOTOP)
Fig.
7.3: Gas-seal testing of a metal gasholder. 1 Place the gasholder in position
with the gas valve closed. 2 Mark the top edge of the digester neck on the
gasholder. 3 Check the location of the mark one day later. 4 If the mark is
found to have dropped by 1-3 cm, use soapy water to check for leaks in the
gasholder. (Source: OEKOTOP)
Fig.
7.4: Pressure testing a gas pipe. 1 Close all gas valves and fill the water
trap. Find the maximum pipe pressure, i.e. how high the pressure in the pipe can
go until the water trap blows off (not more than 50 cmWG). 2 Adjust the test
pressure with the aid of a manometer-equipped test pump or the gasholder (10%
below max. pressure). Check the pressure loss after one day. 3 Use soapy water
to detect leaks. (Source: OEKOTOP)
Pressure testing of the gas pipe
The test must be performed
while all gas pipe connections are still accessible. Pressurize the gas pipe
with the aid of a test pump or by placing weights on the gasholder. If there is
no noticeable loss of gas after one day, the pipe may be regarded as gaslight.
Initial filling of the plant
The initial filling for a new biogas plant should, if possible, consist of either digested slurry from another plant or cattle dung. It is advisable to start collecting cattle dung during the construction phase in order to have enough by the time the plant is finished. When the plant is being filled for the first time, the substrate can be diluted with more water than usual.
Starting the plant
Depending on the type of substrate in use, the plant may need from several days to several weeks to achieve a stable digesting process. Cattle dung can usually be expected to yield good gas production within one or two days. The breaking-in period is characterized by:
- low-quality biogas containing more than 60%
CO2
- very odorous biogas
- sinking pH end
- erratic gas
production.
The digesting process will stabilize more quickly if the slurry is agitated frequently and intensively. Only if the process shows extreme resistance to stabilization should lime or more cattle dung be added in order to balance with pH. No additional biomass should be put into the biogas plant during the remainder of the starting phase. Once the process has stabilized, the large volume of unfermented biomass will give rise to a high rate of gas production. Regular loading can commence after gas production has dropped off to the intended level.
As soon as the biogas becomes reliably combustible, it can be used for the intended purposes. Less-than-optimum performance of the appliances due to inferior gas quality should be regarded as acceptable at first. However, the first two gasholder fillings should be vented unused for reasons of safety, since residual oxygen poses an explosion hazard.
User familiarization
The plant owner should be familiarized with the details of plant
operation and maintenance at the time of commissioning. It is important that he
be not only familiarized with the theory of function but given ample opportunity
to practice using all parts of the plant. The user-familiarization procedure
should be built up around an operational/maintenance checklist (cf. table
7.2).
Table 7.1:
Checklist for the inspection and acceptance of biogas plants (Source:
OEKOTOP)
Check item |
Nonconformance |
Remedy |
Remarks |
I Interim inspection prior to backfilling | |||
Site |
· unsuitable |
· dismantle/demolish the plant | |
Digester masonry |
· cracked/broken bricks/ stones |
· demolish the masonry |
Fixed-dome plants in particular call for high-quality work. Tearing down the plant at this point is often . the least-painful solution |
|
· seriously false dimen- signs | | |
|
· improperly jointed masonry |
· fix with mortar, incl. foundation | |
inlet/outlet pipes |
· false configuration |
· demolish | |
|
· poor backfilling |
· refill | |
II Final inspection and acceptance | |||
Rendering in digester/ gasholder |
· cracks, sandy rendering, low strength, cavities, poorly worked edges and coving |
a) for the gas space of a fixed-dome plant: replace rendering |
Ensure high-quality work man-ship for fixed-dome plants |
| |
b) for the slurry space: repair or add a new layer of rendering (usually sufficient) | |
Masonry seal coats |
· cracks, flaws, thin spots, voids |
· renew the coating |
(applies only to fixed-dome plants) |
Mixing pit/slurry sotre/displacement pit |
· cracks, poor workman-ship |
· demolish or repair | |
Inlet/outlet pipes |
· plugged, poorly worked transitions |
· remove mortar plug, repair with mortar/ concrete | |
Earth fill |
· insufficient fill height |
· recompact, add | |
|
· poorly compacted earth |
| |
Water-fill check of all component heights(relative): inlet, outlet, digester, gas- holder cf. chapter 7.1 |
for floating-drum plants: | | |
|
· water in mixing pit, too low; water spills over the digester, i.e. digester too low; outlet too low for fixed dome plants: |
· shorten the outlet |
Differentiation must be made between nonconfor mances that impair the plant's function and nonconformances that merely prevent optimal utilization |
|
· water above gas zero line - |
· add wall height to digester | |
| |
· lengthen the outlet | |
| |
· alter the elevation of the | |
| |
a) gas outlet |
|
| |
b) displacement pit |
|
|
· water in mixing pit |
· alteration too much trouble | |
|
· water in displacement pit |
· alteration too much trouble | |
Seal testing (see chapter 7.1 for details) |
for floating-drum plants: | | |
|
· water loss < 2% |
· acceptable as is |
In case of doubt, locate and repair all defects, even if it seems like a lot of trouble at the moment; repairs at a later date would be more troublesome! |
|
· water loss > 10% for fixed-dome plants: |
· repair masonry | |
|
· water loss < 2% |
· acceptable as is | |
|
(pressureless) > 10% |
· repair masonry | |
|
· water loss < 5 % |
· acceptable as is | |
|
(pressurized) > 10% |
· repair masonry | |
Gasholder (of floating- drum plants only) |
·false dimensions,wrong |
· reject gasholder, | |
|
· grade of steel, |
build new one |
|
|
· faulty welds |
· repair welds | |
|
· faulty painting |
· repaint | |
Gas valves |
· stuck valves |
· repair or replace |
Check carefully; defects most likely in the gas system |
|
· missing valves | | |
|
· false water trap | | |
Gas pipe |
· false gradient |
· re-install | |
|
· leak found upon pressure testing |
· repair leaks | |
|
· poor workmanship |
· re-install | |
Gas appliances |
· functional defects |
· repair or replace | |
The operation of a simple biogas plant is relatively uncomplicated. The user must be given all the information and practical assistance he needs before and during the early phases of plant operation.
Collecting substrate
The collection of substrate is a simple matter when combined with work that has to be done anyway, e.g. cleaning the stables. It can be made even easier by arranging for the manure to flow directly into the mixing pit. Experience shows that it is not a good idea to gather dung from fields, roads, etc. or to go to the trouble of elaborately chopping up or otherwise preprocessing plant material for use as substrate. The work involved is usually underestimated, while the motivation is overestimated.
Filling the plant
Filling means: mixing the substrate with water, removing bouyant materials, allowing the fill material to warm up, flushing it into the digester, and removing sand and stones. The simple mixing pit shown in figure 5.16 can handle a daily fill quantity of up to 500 1.
Digested-slurry storage/utilization
The further processing of digested slurry is a critical point in that it can be quite toilsome (cf. chapter 3.4).
In designing the plant, care must be taken to ensure that the
slurry store will be large enough. Fixed-dome plants in particular should be
equipped with an overflow, so that the digested slurry does not have to be
hauled away every day.
Table 7.2: Checklist for the
daily operation and regular maintenance of biogas plants (Source: OEKOTOP)
Daily activities:
- fill the plant
- clean the mixing
pit
- agitate the digester contents
- check the gas pressure
- check
the gasholder contents
- check the appearance and odor of the digested slurry
Weekly/monthly activities:
- remove/use the digested
slurry
- clean and inspect the gas appliances
- check the gas valves,
fittings and appliances for leaks
- inspect the water trap
Annual activities:
- inspect the digester for scum formation
and remove as necessary by opening the plant
- inspect the plant for water
tightness and gas tightness
- pressure-test the gas valves, fittings and
pipes
- check the gasholder for rust and repaint as necessary
Monitoring the process
If the plant is properly started before being handed over to the user, it may be assumed to be in proper working order. The user will have become familiar with what optimum plant operation involves. This is very important, because from then on he himself will have to watch for any appreciable changes in how the plant functions; the main indication of a beginning malfunction is a change in the daily gas output.
The maintenance scope for a biogas plant includes all work and inspections needed to ensure smooth functioning and long service life. To the extent possible, all maintenance work should be done by the user.
Biogas plants can develop a number of operational malfunctions. The most frequent problem, "insufficient gas production", has various causes. Often enough, it takes the work of a "detective" to locate and remedy the trouble. It may be necessary to experiment with and monitor the plant for months on end in cooperation with the user.
Repair measures for biogas plants (cf. table 7.5) are necessary in case of acute malfunctions and as indicated by routine monitoring. Repair measures exceeding simple maintenance work usually require outside assistance, since the user himself may not have the necessary tools or know-how.
It is advisable to have the annual maintenance work mentioned in
chapter 7.3 performed by external artisans With prior experience in biogas
technology. Such maintenance and repair work should be ordered on a contract
basis. Past project experience shows that professional biogas repair and
maintenance services can be very important for ensuring long-term plant
performance. Such services should include general advice, functional testing,
troubleshooting, spare-parts delivery and the performance of repair work.
Table 7.3: Checklist for
troubleshooting in case of insufficient gas production (Source: OEKOTOP)
Quantity and quality of substrate
- low/less daily input
-
excessive dilution with water
Ascertain by control measurements
Gas system leaks
- gasholder
- gas pipe
- valves and
fittings
Ascertain by checking all components and connections for leaks with
the aid of soapy water
Disturbance of the biological process
Indications:
- heavy
odor
- change of color of digested material
- drop in pH
Possible remedial measures:
- inspect the quality of the
substrate
- stop biomass until the process returns to normal
- stabilize
the pH, e.g. with lime
- add cattle dung or healthy slurry
- investigate
the user's filling methods to determine if pollutants or noxious substances
(detergents, pesticides, etc.) are getting into the plant
Table 7.4: Simple-plant
malfunctions and remedial measures (Source: OEKOTOP)
Problem |
Possible cause |
Countermeasures |
Plugged-up inlet pipe |
fibrous substrate |
use rod to unplug the pipe |
Stuck gasholder |
floating scum |
1. turn the gasholder |
| |
2. take off the gasholder |
| |
and remove the scum |
Tilted gasholder |
broken guideframe |
repair |
Low gas production, poor gas quality |
cf. table 7.3 |
cf. table 7.3 |
Receding slurry level |
leak in plant |
repair |
Inadequate gas storage in fixed-dome |
leak in gasholder |
repair |
plants | | |
Stuck gas cocks |
corrosion |
apply oil, ,operate repeatedly |
Leaky gas pipe |
corrosion, inferior workman- |
repair |
|
ship | |
Sudden loss of gas |
- broken gas line |
repair |
|
- blown-off water trap |
refill with water |
|
- open gas cock |
close |
Pulsating gas pressure |
water in the gas pipe |
pump out the pipe, relocate that |
| |
section of pipe |
|
plugged-up gas pipe |
push rod through pipe |
Malfunctioning gas appliances |
cf. chapter 5.5.3 |
cf. chapter 5.5.3 |
Structural damage |
cf. table 7.1 |
cf. table 7.1 |
Table 7.5:
Potential repair situations for simple biogas plants (Source: OEKOTOP)
Damage |
Detection |
Remedial measures |
Damaged masonry and rendering |
Inspection of open plant, subsiding slurry level, |
Inspect the plant and repair any seal test damage; tear down the plant if large cracks are found |
Damaged or broken inlet/outlet pipe |
(see above) |
Replace pipe, repair connection to masonry |
Damaged/leaky fixed-dome plants |
Gas seal test, visual inspection of open plant |
Repair rendering, renew seal coatings |
Damaged/corroded gasholder |
High gas losses, seal test |
Replace gasholder, renew weldings |
Broken guide frame |
Tilted/immobile gasholder |
Remove gasholder, repair guide frame |
Leaky/broken/corroded gas pipe |
High gas losses, gas seal test of pipe |
Locate damage, repair or replace as necessary |
Damaged valves/fittings |
Functional inspection |
as a rule: replace |
Damaged gas appliances |
Functional inspection |
cf. "Gas appliances" |
Biogas is a combustible, explosive gas. Its safe handling and
use can be ensured, or at least promoted, by:
- educational measures and
operating instructions
- good, careful planning and execution
- timely
detection of damage and gas leaks
- installation of safety equipment
Safety aspects of planning and implementation
The following basic rules should be adhered to:
- plant
located outside of buildings used for other purposes, e.g. stablings
-
underground installation of pipes
- no use of hoses
- careful installation
and regular inspection of gas pipes
- regular inspection of gas
appliances
- good ventilation of rooms containing gas appliances without
safety pilots
- installation of safety stop valves
- one directly on the
plant, and another on each appliance.
Educational measures and operating instructions
The user must be made fully aware of the explosive nature of
biogas, possibly by way of demonstration (e.g. by producing a flash flame). He
must learn by heart the following basic rules:
- Never leave an open flame
unattended!
- Always close the gas and safety valves of each appliance
properly and immediately after each use!
- Close the plant's safety valves
each night and whenever the plant is left unattended!
Experience shows that leaks and open gas cocks can be detected very quickly, i.e. before an explosive mixture forms, by watching for the conspicuous odor of unburned biogas.
Safety devices
As long as the above safety aspects are
adhered to, small biogas plants in rural areas require few or no special safety
devices, the one major exception being appliances that operate on their own,
i.e. refrigerators, radiant heaters, etc., in which case the use of safety
pilots is
obligatory.